10/29/2019 Update

NJDEP did not issue their decision on the water permit applications on October 25, 2019 as was expected. 

Rather:

  1. Williams/Transco asked for a 30-day extension for a DEP decision on the Flood Hazard Area permit, and
  2. Williams/Transco withdrew their permit applications for Waterfront Development with Section 401 Water Quality Certification & Coastal Zone Management Consistency, and they submitted new applications three days later – October 28, 2019.

      The NJDEP does not have a 90-day decision deadline to adhere to for the Freshwater Wetlands permit application (i.e., There would be no consequences if they rendered a decision on this beyond 90 days after declaring the application to be complete for review.)

      THANK YOU!

      This is to recognize all the recent efforts to ensure that the NJDEP was aware of our concerns, issues with the applications, and recognition that the applications did not meet the stringent standards that the NJDEP was required to adhere to.  Prior to the NJDEP’s anticipated 10/25/19 decision on the June 12, 2019 applications:

      • Franklin Township Council passed a resolution urging the NJDEP to reject the June 2019 permits for the Northeast Supply Enhancement (NESE) Project at their 10/22/19 meeting.
      • Princeton Council passed a resolution urging the NJDEP to reject the June 2019 permits for the Northeast Supply Enhancement (NESE) Project at their 10/14/19 meeting.
      • Letters were sent to the Governor and NJDEP’s Commissioner McCabe from 33 elected officials and 32 organizations or their members urging the DEP to deny the permits for NESE on 10/18/19.
      • Nearly 6,000 people signed letters and/or online petitions/letters from New Jersey League of Conservation Voters, Sierra Club, Food and Water Watch, Clean Ocean Action, Central Jersey Environmental Defenders, and the Natural Resources Defense Council stating opposition to NESE and urging the DEP to deny the permits for NESE.  
      • Over 200 people called the Governor’s office to urge the DEP to deny the permits for NESE because they did not meet stringent regulatory standards
      • Many individuals sent individually-prepared comments to the NJDEP.
      • Franklin Twp. Manager sent extensive comments from the Franklin Township Task Force to the NJDEP and other officials in Trenton on 8/20/19 and 10/21/19.
      • Eastern Environmental Law Center and Princeton Hydro sent comments to the NJDEP on 8/2/19, 8/23/19, 10/21/19, and 10/24/19.
      • People rallied in Red Bank on 9/14/19 at an event organized by Clean Ocean Action.
      • And there were more actions …

      Some of the reasons cited for denying the permits were:

      1. Construction of the NESE Project threatens surface water quality, increased stormwater flooding, and threatened & endangered species and their habitats.
        • From construction in Raritan Bay –  
          • Unearthing toxics above levels acceptable in the regulations
          • Generating turbidity (clouding the water) that would interfere with designated use of the waters
        • From construction of the Madison Loop –
          • Digging in acid-producing soils would result in poor re-vegetation on steep slopes and could lead to excess runoff into wetlands (some of which are classified as “exceptional resource”).
        • From the design of the retention basin for Compressor Station 206 – 
          • This will not adequately address stormwater runoff.
          • NOTE:  Williams/Transco made similar errors that NJ DEP failed to detect and correct in the design and construction of a recent compressor station in Chesterfield Township (“Garden State Expansion” project).
      2. Construction of the Raritan Bay Loop, with its newly proposed shorter schedule, threatens the health of marine life, habitats, benthic and shellfish communities, and the economy of the region due to suspension and spreading of toxins from beneath the seafloor, noise from construction, and limited access to construction space in the Bay for commercial and recreational activities.
      3. Williams/Transco did not demonstrate that there are no practicable alternatives to avoid impacting exceptional resource value wetlands and their transition areas at the proposed CS206 site and Madison Loop.
      4. NJDEP explained that Williams/Transco did not demonstrate (1) that the proposed NESE Project serves an essential health or safety need of the municipality in which it is proposed; (2) that the proposed NESE Project serves existing needs of residents of the State; and (3) that there is no other means available to meet the established public need.
        • NESE does not meet the “public interest” criteria because: 
          • There is no “compelling public need” for it – It does not provide a public health or safety benefit, and, additionally, NY does not need this gas.  Rather, NESE:
            • threatens our air and water quality from methane and other toxic releases, 
            • negatively impacts the health of people and marine/wild life from Compressor Station 206 emissions & unearthed toxins from constructing in Raritan Bay,
            • poses safety risks (fires or explosions) from increased velocity of transporting natural gas through pipelines that are 50+ year old which will impact the rate of corrosion, and 
            • increases risks of flooding at the CS206 site from an inadequately designed retention basin.
        • It doesn’t preserve natural resources, and
          • There would be a negative impact on the shore economy by dredging up toxins from the floor of the Bay which would harm the health and safety of marine life and of Bayshore communities.
          • NOTE:  FERC’s 5/3/19 Certificate of Public Convenience & Necessity was not based on criteria NJDEP needs to use to determine public interest / compelling public need.
      5. The NESE Project’s greenhouse gas emissions and methane leaks would undercut the State’s goals to address impacts on Climate Change.  Based on the responses from the public and political leaders, there is growing support for these goals and opposition to NESE.
        • Approximately 6,000 people called the Governor and/or signed online petitions to the NJDEP and/or to Governor Murphy that included reasons for the NJDEP to deny the June 12, 2019 permit applications.  More comments were emailed or submitted in writing to the NJDEP during the comment period for this 3rd set of applications, but we do not know how many.
        • Governor Cuomo & Mayor DeBlasio, along with many other elected officials in NJ & NY, have voiced their opposition to the NESE Project.

      REMEMBER:  The NESE compressor station & pipeline can’t be built without permits from the NJDEP.

      STAY TUNED for plans for future actions.